Baltic Eagle project monopile production ends

In December 2022, as scheduled, the last monopile for the Baltic Eagle offshore wind project left the production line at EEW Special Pipe Constructions’ Rostock site.

50 monopiles, which have a diameter of between 8.75 and 9 meters, have been steel-structurally completed as well as coated.

"We would like to thank Iberdrola for the trust they have placed in us. So far, everything has gone smoothly and we are delighted to have been able to play our part in the success of the project," says Robert Dreves, Managing Director of EEW SPC.

From spring 2023, the foundations will be float transported to the installation site in the Baltic Sea.